First Gold Production in Q2 2025: Goose Project

Sep 14, 2024

gold pouring illustrativeB2Gold Corp announces an update for the Goose Project in Nunavut, Canada. All planned construction year to date in 2024 has been completed and project construction and development continues to progress on track for first gold pour at the Goose Project in the second quarter of 2025 followed by a ramp up to commercial production in the third quarter of 2025:

B2Gold anticipates that once in commercial production the Goose mine will produce approximately 310,000 ounces of gold per year over the first full five years. Sealift offloading performance has increased this summer due to a newly constructed barge ramp, with seven supply vessels received at the Marine Laydown Area (MLA), ahead of schedule, as of early September 2024.

First gold production can be attributed to the one quarter delay in first gold production previously disclosed, combined with the acceleration of capital items that were previously anticipated to occur after first gold production. The acceleration of certain capital items is expected to make the Goose Project a more reliable and de-risked operation upon mill startup.

The accelerated capital items include accelerated purchases of mining equipment versus the previous estimate to ensure continued growth in mining rates through 2025, the building of an accommodation complex at the MLA which will reduce ongoing annual costs associated with running the Winter Ice Road.

B2Gold recognizes that respect and collaboration with the Kitikmeot Inuit Association (KIA) is central to the license to operate in the Back River Gold District and will continue to prioritize developing the project in a manner that recognizes Inuit priorities, addresses concerns, and brings long-term socio-economic benefits to the Kitikmeot Region. B2Gold looks forward to continuing to build on its strong collaboration with the KIA and Kitikmeot Communities.

With the schedule change, the mill is expected to start wet commissioning in the second quarter of 2025 with ramp up to full production in the third quarter of 2025. The Company continues to estimate that gold production in calendar year 2025 will be between 120,000 ounces and 150,000 ounces.

Importantly, the updated mining schedule does not impact the total number of gold ounces the Company expects to produce over the life of mine of the Goose Project. The updated production profile has resulted in the Company estimating that average annual gold production from 2026 to 2030 will be approximately 310,000 ounces per year.

You May Also Like

Facebook Feeds

Cover for Heera Zhaveraat
98,959
Heera Zhaveraat

Heera Zhaveraat

Offical Facebook account of heerazhaveraat.com, homepage for Trade News, Articles and Promotion of D

This message is only visible to admins.
Problem displaying Facebook posts.
Click to show error
Error: No posts available for this Facebook ID

Twitter Feeds

A guru is not just a teacher, but a torchbearer who shows the way through darkness. Gratitude to all who guide us, today and always. May the blessings of your guru always protect you and uplift you - from Team Laxmi Diamonds Bengaluru

SAJEX 2025: Curtain Raiser in Riyadh just hours away! 💫
After a grand Jeddah launch, the excitement now heads to the capital!
📍 Riyadh | 8th July | Le-Meridien
The SAJEX journey has only just begun!

#Throwback to when Tara Sutaria lit up the NJA stage with elegance! 💫
This year, it gets even brighter.
📩 Submit entries for NJA 2025: https://www.gjc.org.in/nja_segment.php
📞 Shristi Dagar: 93400 31608

Load More

HZ is the Official Supporter of :

Member Of

Founder Member Of